Huaneng Design Institute

Design consulting EPC general contracting project supervision and other whole process professional service institutions

Yantai Hengbang Chemical Co., Ltd. Cogeneration Project

Newly built 2 × 240th boiler 1 × 30MW steam turbine generator set and auxiliary installation project; 8Km steam pipe network installation project from power plant to Yantai brewery.

Binzhou Zhanhua District Maohong New Material Co., Ltd. 1 × 350MW Unit and Auxiliary Installation Project

New 1x1130th Supercritical Boiler 1x 350MW Turbine Generator Set Attached Installation Project, Dongfang Electric Group Dongfang Boiler Co., Ltd., C350300-24.2566566 Steam Turbine, Harbin Steam Turbine Factory Co., Ltd.

Binzhou City Heating Center

Scale: 4 × 240th high temperature and high pressure pulverized coal boiler +4 × 60MW extraction condensing unit and 4 × 480th high temperature and ultra high pressure primary reheat pulverized coal boiler +4 × 150MW unit. The smoke tower integration technology adopted is the only project in Shandong Province and won the third prize for excellent design in Shandong Province.

Inner Mongolia Lingsheng Crop Technology Co., Ltd. Back Pressure Central Heating Project

Scale: 2 × 500 t/h high temperature and high pressure coal-fired circulating fluidized bed boiler 1 × B60MW back pressure unit.

Ningxia Shengyan Industrial Group Fuhua Metallurgical Co., Ltd. Power Station

Scale: 2 × 480th high temperature and ultra high pressure once intermediate reheat circulating fluidized bed boiler 2 × 150MW air-cooled condensing unit.

Engineering Design of Cogeneration Project of Shandong Fengtong Thermal Power Co., Ltd

Scale: 1 x 410th high temperature ultra high pressure pulverized coal furnace 1 x B50MW pumping back unit.

Shandong Xingda New Energy Co., Ltd.

2 × 490th high temperature and ultra-high pressure primary intermediate reheat pulverized coal boiler 2 × C150MW ultra-high pressure unit and 1 × 490th high temperature and ultra-high pressure pulverized coal furnace 1 × B60MW back pressure unit.

Weiqiao Group Huji Power Plant Phase II

Scale: 4 × 1250 subcritical primary intermediate reheat pulverized coal furnace 4 × 350MW unit.

Weiqiao Thermal Power Group Fly Ash Comprehensive Utilization Energy Branch

Scale: 8 × 480 t/h high temperature and high pressure boiler 8 × 60MW pumping back pressure unit, the largest back pressure unit group in China.

Yiyuan Yuaneng Thermal Power Company

Scale: 2 × 260th subcritical ultra-high temperature circulating fluidized bed boiler 2 × B50MW back pressure unit, the first 50MW subcritical ultra-high temperature parameter in China.

Changzhi Huoshi Group Electric Power Company Technical Transformation

Scale: 1 × 480th high temperature and ultra-high pressure circulating fluidized bed boiler 1 × 150MW pumping back unit, the first domestic pumping, condensing and back air cooling unit.