Decision on Project Assessment, Reward and Punishment of Huaneng Longdong Energy Co., Ltd. in 2023
Huaneng Longdong Energy Co., Ltd. Document Huaneng Longdong Fa [2024] No. 7 Decision on Rewards and Punishments for Violation of Red Line in 2023 Departments, Project Departments and Stations: In order to ensure the effective implementation of "Huaneng Longdong Energy Co., Ltd. Violation of Red Line Points and Rewards and Punishments (Trial)", further implement and improve its supervision and reward and punishment mechanism, let all staff participate in safety management work, at the same time, in order to encourage employees to abide by regulations and discipline, according to the accumulated violation red line points of various departments and participating units in 2023 and relevant management systems, the company's general manager's office will study and decide the rewards and punishments as follows: (I) violation red line points above 100 points 1. to the scores of various departments and participating units 1.B2 Project Department violation red line accumulated points: 130 points; 2. Shandong Huaneng Supervision A1 Project Department violation red line accumulated points: 130 points; 3. Cumulative points of violation red line of safety and quality department: 120 points; 4. Cumulative points of violation red line of production department: 120 points; 5. Cumulative points of violation red line of C1 Project Department: 120 points; 6.A1 Cumulative points of violation red line of project department: 120 points; 7. Cumulative points of violation red line of engineering department: 118 points; 8.C2 Project Department's cumulative points of violation red line: 110 points. (II) violation red line points below 100 points 1. Longdian Supervision B2 Project Department violation red line cumulative points: 90 points; 2. Zhongda 'an Company C1 Supervision Project Department violation red line cumulative points: 90 points; 3. Gansu Huayan C2 Supervision Department violation red line cumulative points: 90 points; 4. Dongdian No.1 Company C2 Project Department violation red line cumulative points: 80 points; 5. Shandong Electric Power Construction B2 Project Department violation red line cumulative points: 80 points; 6. Accumulated points of violation red line of nuclear power project A1 project department: 80 points; 7. Accumulated points of violation red line of Tianjin Electric Power Construction C1 Project Department: 80 points; 8. Accumulated points of violation red line of B2 Project Department of Dongdian No.1 Company: 60 points; 9. Accumulated points of violation red line of A1 Project Department of Northwest Electric Power Construction: 60 points; 10. Accumulated points of violation red line of B2 Project Department of Jiangxi Hydropower: 11: 60 points. Rewards and Punishments of 2. Departments and Participating Units (I) Rewards and Punishments According to the relevant provisions of "Measures for Red Line Points and Rewards and Punishments for Violation of Huaneng Longdong Energy Co., Ltd. (Trial)" and the safety, quality, progress and completion of safety work of various projects in 2023, the comprehensive consideration of rewards is as follows: 1.B2 Project Department Rewards 10000 Yuan Shandong Environmental Energy Supervision A1 Project Department Rewards 3000 yuan 2.C1 Project Department, Safety and Quality Department and Production Department Rewards 5000 yuan Engineering Department Rewards 3000 yuan (II) Assessment Based on the relevant provisions of "Huaneng Longdong Energy Co., Ltd. Violation Red Line Points and Reward and Punishment Measures (Trial)", the assessment is as follows: 1. The C2 Project Department of Dongdian No.1 Company, the B2 Project Department of Shandong Electric Power Construction, the A1 Project Department of Nuclear Power Engineering and the C1 Project Department of Tianjin Electric Power Construction have accumulated 80 points of annual violation red lines; Interviews were conducted with the above four project leaders. 2. The accumulated points of the annual violation red line of B2 Project Department of Dongdian No.1 Company, Northwest Electric Power Construction A1 Project Department, Jiangxi Hydropower B2 Project Department and Jiangxi Hydropower C2 Project Department are all 60 points; For each of the above four project managers, 6000 yuan will be assessed (each project department under its jurisdiction will supervise the payment, otherwise it will be deducted directly from the progress payment according to the relevant system). Huaneng Longdong Energy Co., Ltd. January 19, 2024
Documents of Huaneng Longdong Energy Co., Ltd.
Huaneng Longdongfa [2024] No. 7
Decision on Rewards and Punishments for Violation of Regulations in 2023
Each department, project department and station:
In order to ensure the effective implementation of "Huaneng Longdong Energy Co., Ltd. Violation Red Line Points and Reward and Punishment Measures (Trial)", further implement and improve its supervision and reward and punishment mechanism, let all employees participate in safety management, and compact the requirements of "three management and three musts". At the same time, in order to encourage employees to abide by regulations and discipline, according to the accumulated violation red line points and relevant management systems of various departments and participating units in 2023, the company, the general manager's office decided the company's office is as follows:
Scores of 1. departments and participating units
(I) violation red line points above 100 points
1.B2 Project Department's accumulated points for violation of red lines: 130 points;
2. Accumulated points of violation red line of A1 Project Department of Shandong Environmental Energy Supervision: 130 points;
3. Accumulated points of violation red line of safety and quality department: 120 points;
4. Cumulative points of red line violation of production department: 120 points;
5.C1 Project Department's accumulated points for violation of red lines: 120 points;
6.A1 Project Department's accumulated points for violation of red lines: 120 points;
7. Engineering Department's accumulated points for violation of red lines: 118 points;
8. Cumulative points of violation red line of C2 Project Department: 110 points.
(II) violation red line points below 100 points
1. Accumulated points for violation of red line in B2 Project Department of Longdian Supervision: 90 points;
2. Accumulated points of violation red line of C1 Supervision Project Department of Zhongda 'an Company: 90 points;
3. Accumulated points of violation red line of C2 Supervision Department of Huayan, Gansu: 90 points;
4. Accumulated points of violation red line of C2 Project Department of Dongdian No.1 Company: 80 points;
5. Accumulated points of illegal red line of Shandong Electric Power Construction B2 Project Department: 80 points;
6. Accumulated points of violation red line of A1 project department of nuclear power project: 80 points;
7. Accumulated points of violation red line of Tianjin Electric Power Construction C1 Project Department: 80 points;
8. Accumulated points for violation of red line in B2 Project Department of Dongdian No.1 Company: 60 points;
9. Accumulated points of violation red line of A1 Project Department of Northwest Electric Power Construction: 60 points;
10. Accumulated points of illegal red line of Jiangxi Hydropower B2 Project Department: 60 points;
11. Accumulated points of violation red line of Jiangxi Hydropower C2 Project Department: 60 points.
Rewards and punishments of 2. departments and participating units
(I) rewards
According to "Huaneng Longdong Energy Co., Ltd. Violation of Red Line Points and Reward and Punishment Measures"
(Trial) "and the relevant provisions of the project safety, quality, progress and safety work completion in 2023, comprehensive consideration of the reward is as follows:
1.B2 Project Department Rewards 10000 yuan
Shandong Environmental Energy Supervision A1 Project Department Rewards 3000 yuan
2.C1 Project Department, Safety and Quality Department and Production Department each reward 5000 yuan
Engineering Department Rewards 3000 yuan
(II) assessment
According to the relevant provisions of "Huaneng Longdong Energy Co., Ltd. Violation Red Line Points and Reward and Punishment Measures (Trial)", the assessment is as follows:
1. The C2 Project Department of Dongdian No.1 Company, the B2 Project Department of Shandong Electric Power Construction, the A1 Project Department of Nuclear Power Engineering and the C1 Project Department of Tianjin Electric Power Construction have accumulated 80 points of annual violation red lines; Interviews were conducted with the above four project leaders.
2. The accumulated points of the annual violation red line of B2 Project Department of Dongdian No.1 Company, Northwest Electric Power Construction A1 Project Department, Jiangxi Hydropower B2 Project Department and Jiangxi Hydropower C2 Project Department are all 60 points; For each of the above four project managers, 6000 yuan will be assessed (each project department under its jurisdiction will supervise the payment, otherwise it will be deducted directly from the progress payment according to the relevant system).
Huaneng Longdong
Energy Limited Liability
Company
January 19, 2024