Shandong Feicheng 300MW/1800MWh Advanced Compressed Air Energy Storage National Demonstration Power Station Successfully Connected for the First Time
Feicheng, Shandong300MW/1800MWhAdvanced compressed air energy storage
The national demonstration power station was successfully connected to the grid for the first time.

Figure I Feicheng, Shandong300MWAdvanced Compressed Air Energy Storage National Demonstration Power Station
4Month30Day morning11When18The first set of Shandong Feicheng International with completely independent intellectual property rights.300MW/1800MWhAdvanced compressed air energy storage national demonstration power station for the first time grid-connected power generation a success. The power station adoptsInstitute of Engineering Thermophysics, Chinese Academy of SciencesIndependent research and development of advanced compressed air energy storage technology,China Storage National Energy (Beijing) Technology Co., Ltd.as an investment and construction unit,Shandong Huaneng Design Institute Co., Ltd.Responsible for the design, is currently internationallyLargest scale, highest efficiency, best performance, lowest costThe new compressed air energy storage power station.

Figure II Feicheng, Shandong300MWAdvanced Compressed Air Energy Storage National Demonstration Power Station Control Room
The construction scale of the power station is300MW/1800MWhTotal Project Investment14.96Billion yuan, system rated design efficiency72.1%. Continuous discharge can be realized6Hours, annual power generation approx.6Billion degrees, in the peak of electricity consumption is about.20-30Ten thousand households provide electricity protection, which can save about standard coal every year.18.910,000 tons, reducing carbon dioxide emissions by about49Tons.
The power station uses the abundant underground salt cavern resources in Feicheng City, Shandong Province to store gas, and uses air as a medium to realize large-scale power storage on the power grid side. It can provide power regulation functions such as peak adjustment, frequency modulation, phase adjustment, backup, black start, etc. for the power grid, and effectively support the smooth and efficient operation of the power system.

Figure III Feicheng, Shandong300MWAdvanced Compressed Air Energy Storage National Demonstration Power Plant

Figure IV Feicheng, Shandong300MWAdvanced Compressed Air Energy Storage National Demonstration Power Station Booster Station
Feicheng300MWWith the support of governments at all levels in Shandong Province, the Development and Reform Commission, and the Energy Bureau, and with the help of the special grid-connected service of the State Grid Shandong Electric Power Company, the advanced compressed air energy storage project has been successfully connected to the grid for power generation. It is an important milestone in the field of compressed air energy storage, which can effectively promote the rapid development of compressed air energy storage technology and industry, and further consolidate China's international leading position in the field of compressed air energy storage, it lays a solid foundation for the large-scale popularization and application of this technology.
Shandong Huaneng Design Institute Co., Ltd., as a strategic partner of China Reserve National Energy, has been2020years sincesuccessivelyParticipationZhangjiakou, Hebei100MWAdvanced Compressed Air Energy Storage National Demonstration Power Station Project, Nanjing Future Energy System Research Institute100MWcompressed air energy storage project,Feicheng, Shandong300MWAdvanced Compressed Air Energy Storage National Demonstration Power Station, Datang Zhongning100MW/400MWhThe preliminary design and construction drawing design of a number of compressed air energy storage projects, such as the compressed air energy storage project, have accumulated rich design experience, and made outstanding contributions to the expansion and strengthening of the compressed air energy storage industry and the creation of new energy storage productivity!!!