Huaneng Design Institute

Design consulting EPC general contracting project supervision and other whole process professional service institutions

Shandong Feicheng 100 MW Advanced Compressed Air Energy Storage Power Station

300 MW1800MWh, scheduled to be put into operation in December 2023

Comprehensive Energy Demonstration Project of Zhangbei Juchu New Energy Technology Co., Ltd.

Energy storage system engineering (100 MW600MWh), which has been put into operation in 2021

Relocation Project of Section #7-#11 of 500KV Yuanlian II Line

It is the first EHV grade line EPC project completed by our company. The project scale is 500kV Yuanlian II Line #7-11 section line relocation, including the whole design, equipment and materials procurement, construction, trial operation and completion acceptance. The whole construction coincided with the tense time of the epidemic. Through the hard work of the whole company to the project department, the power will be sent and put into production by the end of April 2022.

Benxi City Xihu District Early Shed to Outside Supporting Heating Infrastructure Construction Project EPC General Contract

The main contents of the project are to dismantle the 3x 29MW hot water boiler and 3x 58MW hot water boiler in the original factory area, retain the original 2x75th steam boiler, build a new 2x 98MW hot water boiler, build a 4200m ² closed coal storage yard in the old building, build a 4000m ² dry coal shed, build a 800m2 closed slag yard, build two 1000m ³ closed ash warehouses, and other necessary production ancillary facilities; at the same time, the environmental protection equipment upgrading project of 2 75th steam boilers was completed, and flue gas desulfurization, denitration and dust removal devices were added.

Hehui Dashiqiao 200MW Wind Power Project EPC General Contracting Project

Through the continuous expansion of business work, we have completed the undertaking performance of our company's large-scale wind power general contracting project. The total cost of the overall project is 1.354 billion yuan. The main project is 40 5MW wind power units, and the collector line is connected to the new 220kV booster station in the plant. At present, the civil engineering of the booster station has been basically completed, the main transformer has been hoisted in place, the 13# bearing platform has been completed, and the 33# foundation pit has been excavated. The overall project is planned to be put into operation in June 2024.